Gravel for a French drain: stone size and how much to order
Washed #57, a trench you can calculate in your head, and the fabric question that starts arguments — settled the practical way.
A French drain is just a gravel-filled trench with a perforated pipe in it, but two choices decide whether it works for twenty years or clogs in three: the stone, and whether you wrap the trench in fabric. The amount is the easy part.
The stone: washed #57, not pea gravel
You want clean, washed, angular ½–1 inch stone — #57 — with no fines. Water moves through the gaps between stones; fines and dust clog those gaps. Pea gravel is round, packs tighter, and flows slower; crusher run is full of dust and is flatly wrong here. If the yard's #57 looks dusty, ask when it was washed, or hose a sample — drain stone should look like the pile in the "washed" bin, because it matters.
How much: trench volume, minus the pipe, plus the top
Standard trench: 12 inches wide, 18–24 inches deep. The math for a 50 ft run at 12 in wide × 18 in deep:
- Trench volume: 50 × 1 × 1.5 = 75 cu ft = 2.78 yd³.
- Pipe displacement: a 4-inch pipe takes up about 0.09 cu ft per foot — roughly 4.4 cu ft over the run. Small, but real: call it 0.15 yd³.
- Order: ~2.6 yd³ of #57 at 1.35 t/yd³ ≈ 3.5 tons. Add the 10% allowance → 4 tons.
The gravel calculator does trench math fine — treat the trench as a rectangle, length × width, with the depth in inches.
The fabric question
Line the trench with a non-woven geotextile, lay stone and pipe, fold the fabric over the top like a burrito, then cover with a few inches of soil or decorative stone. The fabric keeps soil from migrating into the stone — the #1 cause of dead drains. What you should not do is wrap the pipe itself in a fabric sock and skip the trench lining: socks clog, and when they do, you're digging up the whole run instead of nothing. Burrito the trench, not the pipe.
A French drain with perfect stone and no slope is a gravel-filled bathtub. Minimum 1% grade — an inch of fall every 8 feet — toward the outlet, and the outlet must daylight somewhere lower or reach a dry well. Check the slope with a level and a marked board before the stone goes in; afterward, checking means digging.